October 9, 2003
ADDENDUM NO. 1

Addendum No. 1
NOTICE TO DOTD CONSULTANT NOTIFICATION LIST:

TIMED PROJECT
STATE PROJECT NO. 700-30-0061
FEDERAL AID PROJECT NO.
LILLIE - ARKANSAS STATE LINE
ROUTE US 167
UNION PARISH



The Compensation as indicated in the Advertisement for the captioned project is hereby deleted and modified to read:
COMPENSATION

The maximum compensation limitation payable to the Consultant for the required services will be $849,960, subdivided as follows:

Topographic Survey (Phase I, Part 2), Property Survey (Phase II, Part 2), and Base and Final Right-of-Way Maps (Phase II, Parts 3 & 5), non-negotiated lump sum of $191,981.

Title Research Reports and Title Updates* (Phase II, Parts 1 & 4), unit costs with a maximum limitation of $18,700.

Final Plans (Phase III), non-negotiated lump sum of $639,279, subdivided as follows:

Roadway $599,899
Bridge $39,380

*Compensation for furnishing the Title Research Reports will be based on a Unit Price of $200.00 per required report. Compensation for furnishing Title Updates will be based on a Unit Price of $75.00 per required report.


The closing date for the submittal of SF 24-102 for State Project No. 700-30-0061 has not changed to be submitted prior to 2:00 P.M. on Monday, October 13, 2003.



Mark Chenevert, P.E. .
Contract Services Administrator