ENGINEERING, SURVEYING, ENVIRONMENTAL SERVICES
November 22, 2002



State Project No. 700-08-0123
Federal Aid Project No. STP-0801(518)
Hamilton Road Improvements
(I-20 to Benton Road)

Bossier Parish

SERVICES REQUIRED - To provide engineering, environmental, and land surveying services for preliminary and final roadway and bridge plans, topographic survey, Environmental Assessment, geotechnical services (if required), title research reports, property survey, right-of-way maps, title update reports (if required), traffic data, signal design, and street lighting, for the widening of Hamilton Road in Bossier Parish.
MINIMUM PERSONNEL REQUIREMENTS - see detailed advertisement
COMPENSATION - Cost + Fixed Fee, with a Maximum Limitation
CONTRACT TIME - not to exceed 18 months
Advertisement Document


State Project No. 700-42-0108
Federal Aid Project No. BRO-4202(503)
Off-System Bridge Rehabilitation
and Replacement Program

Richland Parish

SERVICES REQUIRED - provide topographic survey, hydraulic studies, environmental clearance, preliminary and final plans, and shop drawing review for the replacement of seven bridges.
MINIMUM PERSONNEL REQUIREMENTS - One registered Professional Civil Engineer, one Registered Professional Land Surveyor, and a corresponding support staff.
COMPENSATION - Predetermined Lump Sum Fee
CONTRACT TIME - will not exceed 200 calendar days
Advertisement Document


State Project No. 700-56-0107
Federal Aid Project No. ENH-5602(501)
Downsville Pedestrian/Bicycle Path
Union Parish

SERVICES REQUIRED - provide preliminary and final engineering plans, topographic survey, environmental categorical exclusion (CE), and Section 4(f), (if required).
MINIMUM PERSONNEL REQUIREMENTS - see detailed advertisement
COMPENSATION - Predetermined Lump Sum Fee
CONTRACT TIME - see detailed advertisement
Advertisement Document


State Project No. 700-62-0009
Federal Aid Project No. BRO-6202(502)
Off-System Bridge Rehabilitation and Replacement Program
West Carroll Parish

SERVICES REQUIRED - provide topographic survey, hydraulic studies, environmental clearance, preliminary and final plans, and shop drawing review for the replacement of one bridge
MINIMUM PERSONNEL REQUIREMENTS - One Registered Professional Civil Engineer, one Registered Professional Land Surveyor, and a corresponding support staff
COMPENSATION - Predetermined Lump Sum
CONTRACT TIME - will not exceed 180 calendar days
Advertisement Document


Qualification statements are to be submitted on "Professional Engineering and Related Services Questionnaire for Specific Project" (Standard Form DOTD 24-102, revised January 2003),
Proposals are to be identified with their respective State Project Number(s), and are to be received prior to 3:00 p.m. on Monday, December 16, 2002 by hand delivery or mail addressed to:

Department of Transportation and Development
Attn: Mr. Hadi Shirazi, P.E.
Consultant Contract Services Administrator
1201 Capitol Access Road, Room 405-T
Baton Rouge, Louisiana 70802-4438 or,
P. O. Box 94245
Baton Rouge, Louisiana 70804-9245
Telephone No.: (225) 379-1989